Friday 21 September 2012

Wimbledon Project










The brief : Build four matching pergolas out of green oak.

All the oak came rough sawn so the first obstacle was to plane it all to the correct thickness then  cut and joint it all to fit, with help from the groundwork's team I aligned all the uprights to the correct height and spacings from one another. The project lasted ten days mainly due to all the planing that had to go on on site!
   The designer and client were both thrilled with the finished result. It was a good learning curve for me and i now relish the opportunity of building more.